Activity A task or unit of work within a project or group of projects which usually:
  • has a specific duration
  • has a logical relationships to other tasks (or activities) in a project.
  • makes use of resources (e.g. people, materials, facilities)
  • has a cost that can be related to it
Activity status An activity's status can be:
  • Planned or Scheduled (not started and not on the critical path)
  • Critical (not started but on the critical path)
  • Started or Working (started and not finished)
  • Actual or Finished (completed)
Activity-on-Arrow Technique
A form of criticaActivity-on-Arrow Technique l path analysis diagram where activities (tasks) are represented by arrows and the start or finish of activities (tasks) are represented by numbers within circles or similar shapes.

Activity-on-Node Technique
A form of critical path analysis diagram where (tasks) are represented by rectangular boxes (nodes) which contain information about the tasks. Sometimes called 'Precedence Networking'

Actual activity
'Real' or 'existing' activities (tasks) that have been completed before the project was last updated or scheduled (usually today's date).

Actual Cost of Work Performed (ACWP)
Actual cost of an activity, group of activities (tasks) or a whole project. When compared to BCWP, permits financial monitoring of project progress

Actual date
Dates on which something actually happens - e.g. the start or finish of a task. Actual dates override all other scheduling constraints.

Actual duration
The calculated or scheduled time between the early start and early finish of a task. All tasks have an actual duration whether they are completed or not.

Alternate resource
A resource that may be substituted when resource scheduling - if the requested resource is not available.

Archiving
Saving the current start and finish dates of tasks so they can be compared with dates from later schedules. Producing archives is a useful way of comparing actual progress to planned progress. Archives are also referred to as "Baselines".

As-Late-As-Possible (ALAP)
An task for which the user requires the early dates to be as late as possible without delaying the early dates of any following tasks.

As-Soon-As-Possible (ASAP)
Usually the default status of an Task - where the user requires the early dates to be as soon as possible.

Availability
The quantity of a resource available at a given time (rather than the quantity needed to complete an Task).

Availability limit
A limit applied to a resource which resource and duration schedule engines use when attempting to schedule within normal resource or total resource limits.

Go to top of this page
Backward Pass
A project scheduling process which determines the latest time that tasks must start and finish if a project is not to be delayed.

Bar Chart
A report format where bars indicate the timing and sequence of tasks (sometimes called a Gantt chart)

Bar Chart Symbols
Characters or symbols used in place of the horizontal bar in a bar chart which may be used to provide additional information (e.g. the status of an Task)

Baseline
A copy of the project schedule for a particular time (usually before the project is started) that can be used for comparison with the current schedule.

Budget
The planned cost for an Task or project.

Budget at Completion (BAC)
The total budget for a project, or part of a project.

Budgeted Cost of Work Performed (BCWP)
The budgeted cost of a project or part of a project - sometimes called 'earned value'. When compared to ACWP, permits financial monitoring of project progress

Budgeted Cost of Work Scheduled (BCWS)
The cost that should have been achieved according to the project baseline dates. When compared to ACWP it is possible to determine if the project is ahead of or behind schedule.

Go to top of this page
Calculate a network
Produce a time schedule for a 'network' of tasks within a project or group of projects.

Calendar
A calendar is a specific combination of days per week, shifts per day and shutdowns. Projects can have a number of calendars to accommodate tasks that work different days and hours.

Cost variance
The difference between the budgeted and actual cost of work performed (BCWP - ACWP).

Critical task
If the latest an activity can start is the earliest it must start, it is critical. Critical tasks show the same early and late dates on the forward pass as on the backward pass and in normally have no float.

Critical path
The longest path(s) through a 'network' of inter-dependent tasks. If any activity on the critical path is delayed, the entire project will be delayed. Many projects have more than one critical path.

Critical path analysis
The project planning process in which activity critical paths are determined using activity-on-node (precedence networking) or activity-on-arrow techniques.

Go to top of this page
Dependency
The relationship between two interdependent tasks in a project or series of projects.

Discontinuous activity
An activity (task) in which the time between the start and finish dates is exceeds its 'real' duration. Usually created in order to satisfy start-to-start and finish-to-finish relationships with other activities (tasks).

Dummy activity
Used to describe an activity which takes zero time to complete or has no work content.

Duration
The scheduled time for an activity to be completed.

Duration scheduler
A project scheduling process that shows activity dates, float and the critical path as a time schedule while also taking account of a project's resource requirements and availabilities. Optimises activity durations in order to maximise the use of resources.

Go to top of this page
Earliest feasible date
The earliest date on which an activity could be scheduled to start based on the scheduled dates of all its predecessors (in the absence of any resource constraints on the activity itself). Calculated by resource scheduling.

Early dates
The earliest dates on which an activity can start and finish (determined by forward pass of time analysis).

Early finish
The earliest dates that an activity can finish without affecting the project duration or activity inter-dependencies.

Early start
The earliest an activity can start without affecting the project duration or activity inter-dependencies.

Earned value
The budgeted cost of a project or part of a project which compared to ACWP, permits financial monitoring of project progress. Sometimes called Budgeted Cost of Work Performed (BCWP).

Estimated Duration
The most accurate and realistic estimate of the duration of an activity.

Go to top of this page
Finish-to-Finish (FF) Link
A relationship between two tasks where the second cannot finish until the first has finished.

Finish-to-Start (FS) Link
A relationship between two tasks where the second cannot start until after the first has finished.

Float
The difference between the time necessary to complete an activity and the time available.

Forward Pass
A project scheduling process in which all activity durations are added up to find the shortest possible project duration and the early start and early finish dates of tasks.

Free Float
The maximum amount by which an activity can be delayed beyond its early dates without delaying any succeeding activity beyond its early dates.

Go to top of this page
Hammock activity
An activity which represents a group of (tasks) and which has a start-to-start link with the first in the group and a finish-to-finish link with the last. A hammock activity usually has an estimated duration of zero and has no links with other activities (tasks).

Hierarchical Coding Structure
A multi-level coding system for tasks in which every code except the one at the top has a 'parent'.

Go to top of this page
Internetwork link
A logic link between tasks in different projects or 'networks'..

Go to top of this page
Key activity
duration and are sometimes known as 'milestone' tasks.

Go to top of this page
Ladder activities
A series of activities (tasks) running in parallel, each linked by a start-to-start and finish-to-finish link.

Lag
A time delay associated with a relationship between tasks in a project - described as either positive or negative. Negative lag is sometimes called "lead."

Lag Link
A finish-to-finish link between tasks.

Late dates
The latest dates on which an activity can start and finish. Determined by a backward pass time analysis.

Late finish
The latest time an activity can finish without delaying a project.

Late start
The latest time an activity can start without delaying a project.

Lead link
A start-to-start link.

Leading activity
An activity without any preceding activity.

Logic delay
The period of time between two linked tasks. (e.g. a coat of paint is one activity and the paint has to dry before the next activity can start).

Logic delay calendar
The calendar which the logic delay must obey. Unless a calendar is specified, the delay follows the calendar of the succeeding activity.

Logic Loop
A logic loop occurs in a project when two or more tasks are mutually dependant. The result is that a forward pass cannot be performed.

Go to top of this page
Management Code
A code system which assigning codes to tasks in order to reflect the management needs of business(es) in the preparation of reports etc.

Milestone
See Key Task

Go to top of this page
Negative Float
Occurs when target dates cannot be scheduled within the specified activity durations and shows the time by which the early date of an activity exceeds its late date.

Network analysis techniques
A general term referring to a variety of planning techniques - e.g. precedence networking, activity-on-arrow, line-of-balance.

Network diagram
A diagram showing the tasks in a project, their sequence and the relationships (links) between them - a 'model' of the project. In the commonly used precedence diagram, tasks are represented by nodes and links are represented by lines. Sometimes called a flowchart, PERT chart, logic drawing, or logic diagram.

Network logic
The logic of a 'network' of tasks within a project describes the order in which tasks in a network are performed and the relationships (links) between the tasks.

Node
A rectangular box in a network which contains information about one activity, e.g. the number and description.

Go to top of this page
Organizational Breakdown Structure (OBS)
A hierarchical structure designed to pinpoint the area of an organization responsible for each part of a project.

Go to top of this page
Physical Percent Complete
The percentage of the work content of an activity that has been achieved.

Plan
A scheme for accomplishing a goal which describes how the goal will be achieved.

Precedence Diagram Method (PDM)
One of the two methods of representing projects as networks of tasks in which the tasks are represented by nodes and the relationships between them by arcs. (The other method - Arrow Diagram, is rarely used.)

Precedence Networking
A form of critical path analysis in which tasks are represented by nodes (rectangular boxes) and dependencies are represented by lines. Also known as activity-on-node technique.

Precedent
Preceding activity.

Precedent Links
Links that define the relationships between tasks and those that logically precede it.

Preceding Activity
An activity (task) that logically precedes another. Preceding tasks (preceding tasks or precedents) can be linked to those which logically succeed them (their successors) by a finish-to-start, start-to-start or finish-to-finish links.

Preceding Float
Float that precedes an task's start date, i.e. the amount of time available between when an task is due to start and when it has to start to avoid delaying other tasks.

Project
A series of tasks having an overall objective where the management of time and resources justifies formal planning.

Project Data
Data which relates to an individual project, e.g. activity descriptions or durations.

Project Date
The project date is the date to which the project has been updated, i.e. 'today's' date or 'time now' which remains current until the project until another project date is entered.

Project structure
A term used to describe the system of dividing a project into a master project and sub-projects or 'networks' of tasks. While each sub-project is a project in its own right, it relates directly to a single task in the master project.

Go to top of this page
Relationship
A logical connection between two tasks.

Remaining duration
The amount of work that remains to be completed after the project date in respect of a task that has started.

Requirement
The quantity of a resource needed to complete a task (as opposed to the quantity available, which is called the resource 'availability').

Resource
Anything required to carry out an task or project (except time) - e.g. people, equipment, funding.

Resource breakdown structure
The hierarchical structure of resources that allows resource reporting and scheduling at the detailed or summary levels.

Resource Histogram
A histogram showing project resource requirements, usage, and availabilities against a time scale.

Resource Levelling
A project scheduling process that optimises resource availabilities against resource needs without compromising task or project completion dates.

Resource Pool
A higher level resource in a resource breakdown structure.

Resource scheduler
A project scheduling process which takes account of the resource requirements and availabilities and shows dates, float and the critical path like a time schedule. Some high-level resource schedulers maximise resource use by altering the durations of certain tasks.

Resource-limited Project
A project where the project duration is determined by the quantity of the resources available.

Go to top of this page
Schedule
A schedule of dates produced by a scheduling 'engine' - e.g a basic time schedule will show date and duration information, float and target dates.

Schedule Dates
Start and finish dates calculated by the scheduling 'engine' (which take into account resource constraints, project logic etc).

Schedule Variance
The difference between the budgeted cost of work performed and the budgeted cost of work scheduled at any point in time (BCWP - BCWS).

Scheduled activity
A task that has not started (i.e. its start date as derived from the forward pass is later than the project date).

Scheduler
The scheduling 'engine' in project management software that carries out time, resource, duration scheduling functions etc.

Shutdown
An irregular non-working period such as a holiday or a closure for maintenance work. Regular non-working periods (e.g weekends) are not shutdowns.

Skills
An attribute that can be assigned to a resource.

Start-to-Start (SS Link)
A relationship between two tasks which indicates that the second cannot start unless the first has already started.

Sub-project
A group of tasks represented as a single task in a higher level of the same project.

Succeeding activity
An activity (task) which logically succeeds another and can be linked to it by finish-to-start, start-to-start or finish-to-finish links.

Succeeding float
The time available between when a task is due to finish and the time when it has to finish to avoid delaying other tasks.

Succeeding links
Succeeding links define the relationships between a task and those which logically succeed it. Links can be finish-to-start, start-to-start or finish-to-finish. In the case of a finish-to-start link, the successor cannot begin until the precedent has finished. In a start-to-start link, the successor starts at the same time as the precedent. In a finish-to-finish link, the successor finishes at the same time as the precedent.

Successors
Succeeding tasks

Go to top of this page
Target date
Dates imposed on a task or project by the user that do not relate to the normal sequence or duration of tasks but determine when a task can start or finish. Target dates are respected during scheduling if possible.

Target finish
A task is scheduled to finish on its target finish (or before) if the task durations and availability of resources (if any) permit.

Target start
An rask is scheduled to start on and not before its target start unless other logic constraints delay it into the future.

Task
See Activity

Time Analysis
An analysis of the logic of activity durations generated by forward and backward pass scheduling which calculates the early and late dates for each activity on a project.

Time scheduler
A project scheduling operation that shows dates, float and the critical path taking into account time only (ignoring resource requirements and availabilities). Will show the knock-on effects of durations that tasks have on each other taking into account links with other networks.

Time-Limited Project
A project in which time, rather than resources, is the major constraining factor. Such projects must be completed by a specific date and are completed by acquiring whatever resources are necessary.

Total Float
The sum of the work periods by which a task can be delayed without delaying project completion. A commonly used calculation fot total float is: 'late finish - early start - duration +1' (one extra time unit is added because the start and finish dates are inclusive).

Trailing Activity
An activity (task) that has no successors.

Go to top of this page
Variance
A discrepancy between the actual and planned performance on a project, either in terms of schedule or cost.

Go to top of this page
Work Breakdown Structure (WBS)
The breakdown of a project in terms of deliverables.

Working
If an task's status is 'working' it is currently being performed (i.e. it has an actual start date but no actual finish date).