Windmill 7.3
 
Features
Business Modelling | Project Modelling | Project Scheduling | Management Information | Reporting | Linking to other Applications

New to Windmill V 7.3  Tag indicates features new or significantly enhanced in version 7.3

Jump to top of page

Business Modelling
Calendars
  • Multiple calendars of variable working week pattern
  • Week patterns can change during project
  • Optional division into periods (up to 99 per day)
  • Multiple holidays definable on each calendar
  • All calendar dates Year 2000 Compliant
  • Show years in two digit 99 or four digit 1999 style - New to Windmill V 7.3
Back one level
Resources
  • Multiple resources within each project
  • Resources defined as 'monitor', 'schedule' or 'cost'
  • Twin resource limits definable:
    • as total availability or permitted peak
    • as variable normal availability profile
  • Resource unit cost may be applied
  • Resource allocation by total value or continuous rate
  • Resource rollup by code and group codes
  • Tasks can be selected/grouped according to resource used
  • Resource may be linked to specified calendar or task calendar
Back one level
Dates/Durations
  • Dates represented by:
    • month/day/year calendar format (9 permutations)
    • show years in two digit 99 or four digit 1999 style - New to Windmill V 7.3
    • week numbers day numbers
    • day numbers
    • numeric (days) scale
    • annual week numbers on bar chart reports
  • Project date/Time now for automatic update on current analysis
  • Free calendar date format on data entry
  • Calendar style pop-up prompt panel for dates

Jump to top of page

Project Modelling
Back one level
Projects
  • Project task logic by precedence or successor logic entry
  • Master project controlling multiple sub-projects
  • Sub-projects each of unlimited task capacity
  • Add logic links directly between tasks in different sub-projects
  • Extract and remotely edit individual sub-projects
Back one level
Tasks
  • Task name identifiers:
    • numeric between 1.00 and 99999.99
    • trim leading spaces and trailing digits
    • alphanumeric task numbering
  • Long and short task description fields
  • Management code for multiple level coding of tasks
  • Task definition as schedule/hammock/dummy/key(milestone)/ parent
  • Task durations:
    • estimated task duration
    • minimum/maximum durations (for scheduling) - New to Windmill V 7.3
    • actual task duration
    • actual complete/remaining durations
  • Link task to any project calendar
  • Target start/finish dates for external date constraints
  • Imposed start/finish dates for manual location of tasks
  • Priority code for use in resource scheduling
  • Flexible hierarchical coding structures:
    • work breakdown structure (WBS)
    • organisational breakdown structure (OBS)
    • responsibility coding structure (RSP)
  • Notepad text entries
  • Maintain a list of application files associated to each task
  • Enter an ongoing diary of notes and events for each task
Back one level
Progress
  • Progress can be monitored by:
    • actual start/finish dates
    • remaining duration
    • expected finish date
    • percent complete
    • percent remaining
    • percent work done
  • Update task progress on data grid
  • Update tasks using mouse on bar chart display
Back one level
Precedence Logic
  • Logic links can be defined as:
    • finish to start, start to start, finish to finish
    • positive/negative logic delays
    • logic delays allocated to project calendars
    • logic links between sub-projects
  • Logic link entry by precedent or successor logic on grid display
  • Add and remove logic links using mouse on bar chart display
  • Add sequential or parallel logic links using toolbar buttons - New to Windmill V 7.3
Back one level
Resource Allocations
  • Resources can be allocated in a number of ways:
    • as a value (budget); either a rate or a total value
    • over part of the task duration with optional delay
  • Completed value of resource expended held
  • Remaining value of resource to task completion held
  • Full support for earned value analysis
Back one level
Organisational Utilities
  • Create sub-projects within a project
  • Copy tasks between sub-projects
  • Delete sub-projects within a project
  • Renumber tasks within a sub-project (numeric task numbers)
  • Create task templates for rapid compilation of projects - New to Windmill V 7.3

Jump to top of page

Project Scheduling
Back one level
Schedule Types
  • Time schedule
  • Resource limited schedules
    • resource limited schedule
    • time limited resource schedule - New to Windmill V 7.3
    • duration schedule - New to Windmill V 7.3
Back one level
Task Scheduling
  • This is achieved automatically by:
    • task precedent logic
    • priority code
    • float
    • specified start dates and progress details
    • target dates
    • maximum/minimum duration limits - New to Windmill V 7.3
    • resource availability
    • permitted resource overload within limits
  • Manually fix tasks in time

Jump to top of page

Management Information
Back one level
Project Information
  • Global project information can be shown as:
    • project completion time
    • project start/finish dates
    • sub-project durations
    • sub-project early/late start and finish dates
    • summary bar chart and resource histogram reports
Back one level
Task Information
  • Task information can be shown as:
    • all task input information
    • task early/late start and finish
    • task actual duration
    • duration complete/remaining
    • total float and free float
    • negative float (super-critical tasks)
    • preceding float (stretched tasks)
    • task working status (future/working/actual)
    • task status (scheduled/critical/resource limited) - New to Windmill V 7.3
    • tasks restrained by resource availabilities - New to Windmill V 7.3
Back one level
Resource Information
  • Resource information can be shown as:
    • resource demand per unit of time (histogram)
    • resource demand consolidated into variable time periods
      • daily, weekly, monthly, quarterly, annual periods
      • average, total, accumulated values
    • s-curve calculation
    • % of total requirement
    • combine resources across group codes
    • earned value analysis based on task work completed
  • Resource demand can be shown by:
    • budget or actual values
    • unit cost of resource
    • task selection within each sub-project
    • current or baseline scheduled dates
    • early or late scheduled dates
  • Spreadsheet display for resource information:
    • display of multiple resource types
    • consolidate values into variable time periods
    • sum different resources into total vlaues
    • copy and paste resource values between applications - New to Windmill V 7.3
    • save worksheets for subsequent load and view of values
Back one level
Baseline Information
  • Multiple baselines within each project
  • Baselines preserve scheduled results for tasks
  • Baseline results available for all reports, bar charts and histograms
  • Partial updating of baselines incorporating changes
Back one level
General Operation
  • Data entry modification by task grid forms
  • Pop-up panels for prompts and confirmations
  • Full data checking
  • Global editing across tasks with search/replace, case change etc. - New to Windmill V 7.3
  • Pull-down menu selection throughout
  • Support of function keys and hot keys
  • Configurable toolbar buttons - New to Windmill V 7.3
  • Help displays on-screen
  • On-screen reports with full select and sort facilities
  • 20 screen report formats
  • User definable screen formats
  • Split screen barchart/histogram display
  • Two-way scrolling and find/goto operations
  • Pop-up panels for filenames and loading sub-projects
  • Fully integrated mouse capability
  • Tips displays on bar charts, grid values and grid titles - New to Windmill V 7.3
  • Print grid functions for instant data printing
  • Direct access to all Standard Reports and Extended Schedulers - New to Windmill V 7.3
  • Configurable pop-up prompts for
    • Management Code
    • Work Breakdown Structure (WBS)
    • Organisational Breakdown Structure (OBS)
    • Responsibility Planning (RSP) codes

Jump to top of page

Reporting
Back one level
Standard Reports
Sample Reports
  • Report styles
    • task data lists
    • bar charts (Gantt charts)
    • histograms
    • project logic diagrams (network diagrams)
  • Report output sent to
    • any Windows printer
    • disk file
    • HTML format for Internet/Intranet - New to Windmill V 7.3
    • screen preview before print
    • Windows Metafile Format - EMF/WMF - New to Windmill V 7.3
    • e-mail support
  • General facilities on reports
    • sub-project and task selection/sorting
    • three levels of colour coded headings for tasks
    • twin logo display in page header
    • full range of font styles and colours supported - New to Windmill V 7.3
    • configurable legends in page footer
    • project titles and revision details in page headers/footers
    • free format notes field in report footer
    • portrait and landscape sizes A4 to A0 supported
    • set a margin on page around report - New to Windmill V 7.3
    • add a gutter to aid top/left binding of page - New to Windmill V 7.3
    • report auto-rotates orientation to fit printer paper - New to Windmill V 7.3
    • print large sized reports in sections on smaller format sheets
  • Key special features for bar charts
    • summary reports with multiple tasks per line
    • configurable grouping of tasks by different methods
    • colour code tasks to custom defined scheme
    • include logic links between tasks
    • colour highlight for critical tasks and logic links
    • comparative bars of current plan against baseline plan
    • zig-zag date style to show work completed against baseline plan - New to Windmill V 7.3
    • add text annotation and symbols
    • horizontal scale project timescale to fit page
    • variable timescale option to give fisheye dates display across page
    • vertical fit selected tasks to page
    • hatching can be used for highlighting on monochrome devices
    • range of parameters can be included in the report
  • Key special features for histograms
    • up to 8 resource profiles can be included in each histogram
    • multiple histograms per page
    • overlaid histogram showing base resource usage and s-curve
    • resource limits and overload highlighted
    • resources can be shown stacked or overlaid
    • styles of block, solid or line available
    • automatic or fixed vertical scaling
  • Key special features for logic diagrams
    • automatic layout of tasks on diagram
    • control over fit to single page or fit to multiple pages
    • Activity on Node and Activity on Arrow formats supported
    • highlight critical tasks and critical logic links
    • mark task progress on diagram - New to Windmill V 7.3
    • colour code tasks to custom defined scheme - New to Windmill V 7.3
    • range of node styles provided - New to Windmill V 7.3

Back one level
Reports Toolkit
Sample Reports
  • Step by step wizard to create fully functional reports - New to Windmill V 7.3
  • User-defined report layout and page design
  • Reports written to printer, file, HTML for Internet/Intranet or screen
  • Command language controlling
    • calculations
    • text manipulation
    • task selection
    • format selection
    • output options
  • Direct parameter substitution into report formats
  • Calculations using Hornet parameters, derived data and user's own parameters
  • Full text variable, mathematical and logical operators
  • Extended report selection options
  • Full colour selection and font control - New to Windmill V 7.3
  • Include line shapes, symbols and image bitmaps on report design
  • Screen editor for report formats and command macros
  • Library management of report formats, commands and other reporting utilities
  • Full range of paper sizes supported
  • Reports written to printer, file, HTML for Internet/Intranet or screen
  • Preview reports before printing
Back one level
Selecting and Sorting
  • Select tasks and sort into sequence for reports and display using
    • range of task numbers
    • range of scheduled dates
    • management code (full or partial match)
    • hierarchical codes
      • Work Breakdown Structure (WBS)
      • Organisational Breakdown Structure (OBS)
      • Responsibility Planning (RSP) codes
    • task float
    • task type
    • resource code
    • task name
    • early/late dates
    • task description
  • Select and sort across sub-projects
  • Group tasks under task number range or coding entries
  • Select and sort tasks by colour anf fill styles
  • Use task selection options in calculating resource profiles
  • Maintain a library of Select and Sort macro files

Jump to top of page

Linking to other applications
  • Hornet Windmill links to most database and spreadsheet application packages through :
    • Comma Separated Value (CSV) sequential files
    • ASCII relative files
    • bi-directional data transfer
  • Copy and paste task details directly from and to the Task Data Grid - New to Windmill V 7.3
  • Copy and paste resource values from and to the Resource Spreadsheet - New to Windmill V 7.3
  • Direct data output to the Hornet XK database SQL databases.
Jump to top of this page
Last Revised December 1998