Q: As I use the Bar Chart display to add logic links between tasks Hornet Windmill sets different calendars for the logic delay period. Why?

A: By default Hornet Windmill sets the calendar for the logic delay period equal to the calendar of the successor task.

For Hornet Windmill version 7.3 and later (32 bit application) you can change the default action by manually editing the system control file HORNET.INI (this will be found in the system Windows directory). You should set the entry for LinkCalId under the [Options] section to the required value:

0
Default - Use the calendar of the successor task;
-1
Use the calendar of the precedent task;
-2
Use the calendar of the current background calendar; if not set then use the calendar of the successor task;
>0
Use the specified calendar as identified by the numeric identifier - Do NOT use this option as the numeric identifiers for calendars can change.