Application example
Building industry contract management
|
Internal/external contracting resource
management
|
|
The Client |
Part of the Dimension
Data Group, GK Electrical specialises in creating simple
solutions to complex engineering design schemes. They have a
distinguished track record in Commercial, Industrial, Process,
Chemical, Pharmaceutical and Food environments, operating across a
wide range of advancing technologies. |
|
The Task |
Optimisation of planning, design, installation and
commissioning resources across multiple projects - together with
improved management of project documentation and clearer
illustration of the status of work in progress. |
|
Background |
At any given time, GK Electrical are managing the design and
installation of many complex commercial and industrial projects. Key
facets of successfully managing projects of this type are the
effective control of project documentation - and visualisation and
management of project costs and progress. After researching Project
Management systems capable of handling both multiple complex
projects and meeting their particular needs, the Company invited
Hornet to offer a solution. |
|
Specification |
At any given time, GK Electrical are managing the design and
installation of many complex commercial and industrial projects. Key
facets of successfully managing projects of this type are the
effective control of project documentation - and visualisation and
management of project costs and progress. After researching Project
Management systems capable of handling both multiple complex
projects and meeting their particular needs, the Company invited
Hornet to offer a solution. |
|
What Hornet did |
To achieve the required specification,Hornet;
- Added Documents Received notes to a standard bar
chart report as a series of coded flags or markers, showing for
example:
-
- Site Instructions;
- Progress Reports;
- Meeting Minutes;
- Technical Information Requests;
- Free Issue Equipment;
- Correspondence;
- added document symbols on the same line as the task in the
bar chart report.
- added an ability to list all documents associated with a
group of tasks down a page - sorted into weekly intervals.
- added a solid fill feature (to represent work completed on a
task) to bar charts drawn against a base line programme.
- added the functional ability to import progress values (dates
of work, sections and man-hours logged) into Hornet from
existing recording system data and list them in tabular format
and show a histogram profile of completed and future workload.
|
|
The Outcome |
GK Electrical now use Hornet extensively - both for internal
project management and for presentation of project work to
Customers.
The Company now has a Project Management System that
facilitates project document management and presentation of the
information in a coherent way - internally and to Customers.
The additional work-in-progress features are providing GK
Electrical with a valuable additional progress monitoring and cost
control tool that is helping them to maintain their competitive
edge.
|