|
Application example
Building industry contract management
|
|
The Client |
Major construction company undertaking medium-sized building and
civil engineering contracts throughout the UK. |
|
The Task |
To improve business efficiency and provide a common house style
to Clients, the Client wished to establish:
- a common platform for project management within the business
- a common but flexible style for all project reports - capable of
meeting the differing needs of managers within the business.
|
|
Background |
The Client's task is to schedule many discrete project tasks
having few logic constraints but within strict resource limits and
required time slots (e.g. digging of cable trenches for BT).
The Client uses Hornet
XK in a Unix environment to schedule many small projects
(principally using the resource scheduler) and
Hornet Windmill
on individual sites for planning construction projects.
|
|
Specification |
Hornet were asked to provide a system that would provide all
Hornet's standard features, and in addition:
- provide a suite of reports included bar charts, progress curves
and tabular reports, all including a specific design for titles and
company logos.
- meet the standard engineering reporting layout for A1 and A0
paper
- provide additional space for notes and other contract details
- include legend panels for contract titles and reference details
and a list of partners that were working with the company on the
contract (architect, electrical contractor, etc.).
- allow automatic insertion of different contract details into
reports prepared for different contracts.
- the options of adding extra data values to the report to meet the
requirements of their users.
- a zig-zag style date line that emphasises where the project is
running ahead or behind schedule. Re-design of Hornet standard
reports to follow a similar style.
|
|
What Hornet did |
In meeting the above specification, Hornet generated three
additional custom reports:
Summary Progress Bar Chart: designed to show:
- the entire contract on a single sheet by grouping tasks under
different section headings, and showing current progress by
depicting the 'worst case' section within each group.
- an option allowing a single section to be printed - listing all
tasks within the group and show the ahead/behind summary bar for
each task in turn (allowing the manager to focus on any sections
causing concern)
Progress Data Report: designed to show:
- summarised tabular progress data for the project.
- a comparison of the current progress of each task - using the
specified Percent Work Done value - applied to both the current
schedule and the original planned schedule dates - the difference
being expressed as a duration, using the finish dates of the tasks
for the measure.
- the value ahead/behind as part of the task data, listing these
values for the current period and the previous period (the reports
can therefore be used to show any trends in sections gaining or
losing time).
- optional limited length reports - by omitting tasks recorded as
complete as well as are tasks that have not been started - allowing
a concise and focused report to be produced.
Progress Histogram Report: designed to show:
- the aggregated and totalled shift production count for all
project tasks (essentially a form of Earned Value where the 'value'
used as the overall measure is a simple count of number of shifts
worked against each task)
- a baseline or archive schedule for the project, defining the
original start and finish dates for all tasks and forming the
baseline for all comparisons of actual progress against the plan.
Current progress is recorded as a specified Percent Work Done value
for each task - determining the value of the work done on each task
as a realistic estimate of true progress (and not a measure of
completed days over planned days). From these values a series of
resource curves or profiles are calculated by
Hornet Windmill.
- a facility to perform a 'duration based' calculation of the
required values without having to set resource values against each
of the project tasks. plot a duration-based calculation of values as
a graphical histogram - showing each series of values as a
cumulative or s-curve style (colour being used to distinguish the
different curves and a legend added to the report footer).
- the effects of task Select and Sort facilities on the above
calculations - permitting focus on a single section of the project
(or in a multi-project environment, provide a separate report for
each project) - making the report a powerful tool in monitoring all
sections of a large project.
|
|
The Outcome |
In addition to achieving the company's common reporting
requirements, the Client received a number of custom reports capable of
providing both detailed and overall analysis of the many projects
undertaken by the company.
The custom reports have been added to
Hornet Windmill
and Hornet XK's
standard Menus so that can be made available to other users.
|